House number 4
- Preparatory work to perform insulation and waterproofing terraces of the 6th floor
- The device insulation and waterproofing of the roof - Section number 3
- Installation of monolithic reinforced concrete offices and pits Section No. 2, No. 3 - 28 m3
- The beginning of work on the facade - Section number 1
House number 3
- Installation of monolithic reinforced concrete offices and pits: Section №1, №2 - 13 m3
- Continuation of work on the device of the facade of the building - Section №1,2,3
- Installation of smoke and ventilation mines and ducts - Section №2
House number 2
- Installation of metal-plastic window constructions of the 2nd and 3rd floors - Section №1
- Brick masonry walls. Section number 1, number 3 of the basement. Floor 6 - Section №1
- The device partitions of gypsum plasterboard plates. Section №1, floor 6
- Installation of aluminum stained glass structures of the 6th floor - Sections No. 2 and No. 3
House number 1
- Concreting of concrete preparation under the device of the base plate - Section №2
- Installation of vertical reinforced concrete structures of the 3rd and 4th floors - Section №1
- Construction of the reinforced concrete slab of the 3rd and 4th floors - Section №1
- Brick walls of the 1st and 2nd floors. Section number 1.