House # 4
- Preliminary work on the insulation and waterproofing of the terraces of the 6th floor
- Roof insulation and waterproofing - Section # 3
- Arrangement of monolithic reinforced concrete input groups and shafts: Section # 2, # 3 - 28 m3
- Start of works on facade arrangement - Section # 1
House # 3
- Arrangement of monolithic reinforced concrete input groups and receptacles: Section # 1, # 2 - 13 m3
- Continuation of works on arrangement of the facade of the building - Section # 1,2,2
- Installation of smoke extraction mines and ventilation ducts - Section # 2
House # 2
- Installation of metal-plastic window structures of the 2nd and 3rd floors - Section # 1
- Brick walls. Sections №1, №3 of the basement floor. Floor 6 - Section # 1
- Arrangement of partitions from gypsum groove plates. Section # 1, Floor: 6
- Installation of aluminum stained glass structures on the 6th floor - Sections No. 2 and No. 3
House # 1
- Concreting of concrete preparation for foundation slab arrangement - Section # 2
- Arrangement of vertical canopy structures of the 3rd and 4th floors - Section # 1
- Arrangement of roof slabs of the 3rd and 4th floors - Section # 1
- Brick laying of walls of 1st and 2nd floors. Section # 1