Planned construction and installation works until 01.05.18. House 1. Facades - 100%, decorative frames of roofs and canopies - 100%, adjoining exit points to the roof - 100%, railings - 100%, plaster of the upper floors - 100%, entrance doors of the upper floors - 100%, glazing of entrance groups - 100%, distribution of gas supply - 100%, storage rooms of the technical floor - 80%, finishing of entrance groups - 50%, framework for installation of boilers - 50%. House 2. Facades - 100%, decorative frames of roofs and sheds - 80%, adjoining exit points to the roof - 100%, railings - 20%, plaster of the upper floors - 100%, entrance doors of the upper floors - 100%, elevators - 100 %, gas distribution layout - 30%, finishing of common areas - 70%, framework for installation of boilers - 50%. House 3. Facades - 100%, decorative frames of roofs and sheds - 80%, adjoining exit points to the roof - 100%, railings - 40%, plaster of the upper floors - 100%, entrance doors of the upper floors - 100%, elevators - 20 %, distribution of gas supply - 60%, storage rooms of the technical floor - 50%, finishing of common areas - 70%, framework for installation of boilers - 50%. Intra quarter water supply networks of the first stage - 80% Intra quarter first sewage networks - 80% Intraquarter first-line stormwater networks - 40% Intra quarter gas supply networks of the first stage - 30% Intra quarter power supply networks of the first stage - 30% Kindergarten. The laying of the second floor - 50% Fountain. Monolithic structures of the bowl and engine room - 80% Planned construction and installation works until 01.05.18. second phase of construction. House 4. Walls and partitions - 100%, smoke panels 80%, apartment windows - 100%, electrical wiring of the upper floors - 50%, screed of the upper floors - 20%. House 5. Walls and partitions - 100%, smoke panels 60%, apartment windows - 90%, electrical wiring of the upper floors - 50%, screed of the upper floors - 20%. House 6. Walls and partitions - 100%, smoke filters 70%, apartment windows - 50%, electrical wiring of the upper floors - 50%, screed of the upper floors - 20%.