Section № 2
• Stoning inside. partitions from the groove block on the 12th floor.
• Installation of aluminum structures 1,2 floor
• Stoning inside. walls and partitions of brick and groove on the 6th floor.
• Stoning inside. walls and partitions of brick and groove on the 5th floor.
• Stoning inside. walls and partitions of brick and groove on the 4th floor.
• Stoning inside. partitions from the groove block on the 3rd floor.
• Installation of AirVent 21x62 type ventilation units on the roof.
• Completion of facade works "Capture 5.6".
• Brick walls in the parking lot
• Exterior and interior walls. brick walls on the 1st floor.
• Exterior and interior walls. brick walls on the 2nd floor.
Section № 1
• Exterior wall enclosing brick walls.
• Installation of aluminum structures 1,2 floor
• Exterior and interior walls. brick walls on the 1st floor.
• Exterior and interior walls. brick walls on the 2nd floor.
• Installation of double-glazed windows from 3rd to 11th floor.
• Installation of AirVent 21x62 type ventilation units on the roof.
• Brick walls in the parking lot
• Arrangement of waterproofing in the village from 3rd to 12th floor inclusive.
Section № 3
• Plastering of walls from 4th to 10th floor inclusive.
• Laying of electrical networks from 3rd to 11th floor.
• Completion of facade works "Capture 1,2,3,4".
• External mounting drainage system on the facade.
• Arrangement of waterproofing in the village from 3rd to 11th floor inclusive.
• Brick walls in the parking lot