House number 4. Completed 95% of the facade. Roof device 100%. Plaster walls 90%. Screeds 40%. Work is underway on electrical wiring, water supply, sewage, heating. Installed aluminum frame designs of the input groups. House number 5. Installed 90% of windows. Plaster walls 65%. Facades 65%. Roof 90%. Work is underway on electrical wiring, water supply, sewage, heating. House number 6. Installed 100% of the windows. Plaster walls 65%, Roofs 90%. facades of 35%. Work is underway on electrical wiring, water supply, sewage, heating. Dismantled tower crane.