House number 4. Completed 80% of the facade. Completed works on the installation of house electrical wiring of entrance number 2. Roof device 60%. Plaster walls 80%. Planned execution of works until 04.11.2018: execution of the facade 90%, plaster 95%, roofing 95%, heating wiring 50%, screed 30%. House number 5. Installed 60% of windows. Plaster walls 35%. Facades of 25%. Work has begun on the device wiring and wiring heating. Planned execution of works until 04.11.2018: execution of the facade 60%, installation of windows 85%, roofing 50%, plastering of walls 60%, starting work on floor screeding. House number 6. Completed 85% of smoke and ventilation ducts. Installed 85% of windows. Plaster walls 30%, Roofs 50%. Planned work to be done until 04.11.2018: 100% window installation, 90% roofing, 80% plastering.