Completion of RC “Riverside” for October 2019

House # 1 p.1
1. Installation of monolithic reinforced concrete railings
2. Installation of window frames 3 floor
3. Installation of window frames 4 floor
4. Warming of facade with mineral wool 150mm thick
5. Installation of double-glazed windows 1-4 floors
6. Installation of ladders 100%

  House # 1 p.2
1. Arrangement of vertical reinforced concrete structures 7 floors
2. Installation of monolithic reinforced concrete floor 7 floors
3. Arrangement of monolithic reinforced concrete railings
4. Installation of precast blocks 2-3 floors
5. Installation of window frames 3 floor
6. Installation of window frames 4 floor
7. Installation of window frames 5 floor
9. Brick laying of external and internal walls 3-6 floors
10. Installation of ladder marches to adm. 100%

Improvement between Building # 1 and Channel
1. Backfilling of basement walls
2. Arrangement of the banks of the canal reinforced concrete piles
3. Vertical soil planning for improvement
4. Arrangement of reinforced concrete piles under the bridge

  House # 2 p.4
1. Installation of monolithic reinforced concrete floor 5 floors
2. Arrangement of vertical reinforced concrete structures 6 floors
3. Arrangement of monolithic reinforced concrete floor 6 floors
4. Brick masonry of exterior and interior walls of 1 floor
5. Brick masonry of exterior and interior walls of 2 floors
6. Brick laying of exterior and interior walls of 3 floors
7. Brick laying of exterior and interior walls 4 floors

House # 2 p.4
1. Arrangement of monolithic reinforced concrete floor 3 floors
2. Arrangement of vertical reinforced concrete structures 4 floors
3. Installation of monolithic reinforced concrete floor 5 floors
4. Installation of vertical reinforced concrete structures 5 floors

House # 8 p.3
1. Arrangement of monolithic reinforced concrete foundations of section 2
2. Arrangement of monolithic reinforced concrete foundations of section 3
3. Installation of monolithic reinforced concrete basement walls

House # 9
1. The arrangement of the test presses of the piles

  1st Quarter Housing
1. Geodetic marking of the route for arrangement of external networks
1. Arrangement of access roads, installation of road plates
2. Dismantling and erection of temporary fencing of the construction site decking

×