Comfort LifeAll newsCourse of constructionCompletion of works for October 2019 RC “The Best Quarter”

We build a comfortable life

0
1
2
3
4
5
6
7

Completion of works for October 2019 RC “The Best Quarter”

House # 1.
1. Plastering the walls of the second floor.
2. Roof waterproofing arrangement.
3. Finishing a fragment of the facade of the house.

House # 2.
1. Performing plumbing in the basement.

House # 3.
1. Finishing a fragment of the facade of the house.
2. Performing plumbing in the basement.

House # 4.
1. Plastering of walls of entrance group of the first floor.
2. Performing plumbing in the basement.

House # 5.
1. Finishing a fragment of the facade of the house.

Houses # 6 and # 7.
1. Setting up smoke channels.
2. Installation of metal-plastic window structures of the second floor.
3. Roof waterproofing arrangement.

Houses # 8, # 9.
1. Roofing Exits


House # 10.
1. Arrangement of overlapping of the 3rd floor.
2. Arrangement of brick laying of railings.

Houses # 12 and # 13.
1. Arrangement of the brickwork of the basement floor.
2. Arrangement of the ceiling of the basement floor.

Houses # 14 and # 15.
1. Installation of foundation blocks.

House # 16.
1. Installation of foundation blocks.

Houses # 17 and # 18.
1. Arrangement of reinforced concrete grilles.

×