Works for February 2020. Residential Complex “The Best Quarter”

House No. 1.
1. Insulation of the entrance group.
2. Glazing stained glass fence entrance group.

House No. 2.
1. Glazing stained glass fence entrance group.
2. Insulation of the entrance group.
3. Application of spray in the basement floor MZK.

House No. 3.
1. Glazing stained glass fence entrance group.
2. Spraying in the basement floor MZK.

House No. 4.
1. Arrangement of the stained-glass fence of the entrance group.
2. Spraying in the basement floor MZK.

House No. 5.
1. Painting works in MZK.
2. Installation of laundry rails on terraces.
3. Installation of aluminum frame for staircase fencing of the entrance group.

House No. 6.
1. Installation of laundry rails on terraces.
2. Implementation of works on the installation of plumbing networks of the 3rd floor.
3. Plastering of walls of the third floor.
4. Arrangement of the stained-glass fence of the entrance group.

House No. 7.
1. Plastering the walls of the third floor.
2. Arrangement of the basement entrance group.
3. Installation of aluminum frame for staircase fencing of entrance group.
4. Execution of works on arrangement of plumbing networks of 1-3 th floors.

Houses №8 and № 9.
1. Installation of metal-plastic window structures of the 1st and 2nd floors.
2. Arrangement of metal fencing on the roof.
3. Arrangement of vertical waterproofing and insulation of the basement floor.

House No. 10.
1. Installation of metal fencing on the roof.
2. Arrangement of brickwork and monolithic covering of the entrance group.
3. Arrangement of vertical waterproofing and insulation of the basement floor.

Houses No. 11, No. 12 and No. 13.
1. Installation of metal fencing on the roof.
2. Arrangement of brickwork and monolithic covering of the entrance group.

Houses No. 14 and No. 15.
1. Ground floor overlap arrangement.
2. Arrangement of the brickwork of the second floor.
3. Arrangement of vertical waterproofing and insulation of the basement floor.

House No. 16.
1. Arrangement of vertical waterproofing and insulation of the basement floor.

House № 17.
2. Arrangement of a monolithic reinforcement belt on the walls of the basement floor.

House № 18.
1. Installation of the basement blocks of the basement floor.

Houses №19-23.
1. Preparatory work for the arrangement of the pile field.

×