List of completed works at the Royal Park facility. September 2019

Section # 2
• Masonry of external enclosing walls of thicknesses. 250mm on the 10th floor.
• Laying of internal partitions of solid brick 120 mm thick on the 9th floor.
• Masonry partitions of 80 mm thick tongue-and-groove block on the 9th floor.
• Laying of ventilation shafts on the 9th floor.
• Installation of ventilation units from the 3rd to the 12th floor inclusive.
• Laying of 120mm thick solid brick partitions on the 10th floor.
• Installation of metal clips from the corners into the doorways of the elevator vestibules, from the 7th to the eleventh floor.

Section # 1
• Installation of a monolithic reinforced concrete floor slab of the 12th floor.

Section 3
• Installation of a ventilation system for smoke removal from gas boilers from the 6th to the 9th floor.
• Installation of metal clips from the corners into the doorways of the elevator platforms, from the 6th to the eleventh floor.
• Laying of internal walls of thicknesses. 250mm of 2NF brick on the 7th floor.
• Laying partitions of solid brick thicknesses. 120mm on the 7th floor.
• Laying of partitions from the tongue-and-groove block of thicknesses. 80mm on the 7th floor.
• Installation of mineral wool tovshch. 150mm on a front part (1 capture on Sobornaya St.).
• Installation of a monolithic reinforced concrete parapet on the terrace of the 12th floor.
• Glue application on mineral wool on the front of the building.
• Installation of lightning protection around the perimeter of the building.

×