List of completed works at the “Royal Park” facility October 2019

Section # 2
• Installation of monolithic canopies on the 12th floor (terrace).
• Installation of window frames №9, № 10.

Section # 1
• Installation of monolithic canopies on the 12th floor (terrace).
• Installation of monolithic roof railings.
• Arrangement of a monolithic roof staircase.
• Laying of internal and external walls of thicknesses. 250mm 2NF brick on the 3rd floor.
• Laying partitions made of solid brick thickness. 120mm on the 3rd floor.
• Laying of internal and external walls of thicknesses. 250mm 2NF brick on the 4th floor.

Section # 3
• Installation of ventilation system for smoke removal from gas boilers from the 9th to the roof.
• Laying of internal walls of thicknesses. 250mm 2NF brick on the 8th floor.
• Laying partitions made of solid brick thickness. 120mm on the 8th floor.
• Laying of partitions from a groove block of thicknesses. 80mm on the 8th floor.
• Finishing the facade (1 clamp).
• Roof arrangement.
• Laying of internal walls of thicknesses. 250mm 2NF brick on the 9th floor.
• Laying partitions made of solid brick thickness. 120mm on the 9th floor.
• Laying of internal walls of thicknesses. 250mm of 2NF brick on the 10th floor.
• Laying partitions made of solid brick thickness. 120mm on the 10th floor.
• Application of mineral wool glue on the front of the building (Lock 2).
• Laying brick railings on the roof.
• Installation of lightning protection around the perimeter of the building (Lock 2).

Parking
• Arrangement of vertical monolithic concrete structures.
• Arrangement of the floor slab of the parking lot.

×