As of 04/26/2019:House number 4. Completed 100% of the facade, roofing, plaster, glazing, monolithic pit. Screed flooring 80%. Electricity 90%, water supply 90%, sewage 90%, heating 90%. Installation of elevators started.House number 5. Completed 100% of the roof, glazing. Facade 90%, plaster 75%, electricity 40%, water supply 40%, sewage 40%, heating 40%.House number 6. Completed 100% of the roof, glazing. Facade 95%, plaster 80%, electricity 40%, water supply 40%, sewerage 40%, heating 40%.Began landscaping works along the house 4. Work is underway on the on-site water supply networks, domestic and storm water. sewers.